South Seminole Road Drainage Improvements at-a-Glance

AnnouncementSouthSeminoleDrainageOpenHouse022020The project is located on Seminole Road from David Street to Palm Avenue and consists of the following drainage improvements: reconstruction of residential driveways; grading existing roadside ditches; removal of storm drain pipe; storm drain pipe and drainage structure construction; sidewalk construction; and incidental signing and striping.

On Jan. 27, 2020, the City Commission awarded the drainage project to Gruhn May, Inc., at a cost of $463,060.40, to construct the project in accordance with the plans and bid specifications.  The project is fully funded in the City’s fiscal year 2019-20  budget.  A preconstruction conference will be held on February 19, 2020, at which time a notice-to-proceed date will be determined.  The contractor will be given 120 days to complete the project.

The City will host a South Seminole Road Drainage Improvement Project Open House from 5 to 7 p.m. Thursday, Feb. 20. Drop in anytime to learn about the project. Short presentations will be made at 5:30 and 6:30.

For more information, call or email Public Works Director Scott Williams at (904) 247-5834 or swilliams@coab.us; or call or email Deputy City Manager Kevin Hogencamp at (904) 247-5804 or khogencamp@coab.us.

Click here to view the project map.

Click here to view the project plans.

Click here to view the Jan. 27, 2020, construction agreement staff report.

Click here to view the City Commission resolution awarding the construction agreement.

Click here to view City staff’s contract bid analysis.